Alcoa Jetty Refurbishment
| Operator | ALCOA JETTY REFURBISHMENT |
| Location | JAMAICA |

Retrowrap H Pile outer jacket with associated pre felted pre gelled filler blocks being loaded on work barge.

Full length one piece outer jacket with lag fasteners pre installed.
Note: Ident tag attached to jacket to ensure correct installation location.

Temporary work platform attached to pile to permit upper pile cleaning and attachment of upper seal collar against pile cap.

Full length outer jacket installed.
Note: Radius contour visible across pile flat face.


Jacket and filler blocks installed on 14” vertical and raker piles.

Raker pile cap termination.

Vertical pile cap termination.

Vertical Pile Jacket showing outline (under fabric) of pile cap top seal
Seated at pile/pile cap high stress interface